If 8 man can finish work in 7 days .If 5 man work in 7 days can finish the work. Share with your friends Share 0 Shalu Sharma answered this Since, 8 man in 7 days completes 1 work ⇒ 8 man in 1 day completes 17 part of work ⇒ 1 man in 1 day completes 156 part of work ⇒ 5 man in 1 day completes 156×5 part of work ⇒ 5 man in 7 days completes 156×5×7 part of work =58 part of work 0 View Full Answer