A and B can separately complete a piece of work in 20 days and 30 days respectively,they worked together for some time.then B left the work.if A  completed rest of the work in 10 days then B worked for how many days?please give meaningful step by step answer,not any similar link.

Dear student,

Amount of work done by A in 1 day=120Amount of work done by B in 1 day=130Let B worked for x daysAccording to question,xAmount of work done by A and B in 1 day+10×Amount of work done by A in 1 day=Total workx120+130+10120=1                      [as in fraction 1 is the highest number]x3+260+10×120=1 5x60+12=1   x12=1-12x12=12x=122x=6Thus, B worked for 6 hours

Regards

  • 0
What are you looking for?